The Commonwealth of Massachusetts
has a new retainage law applicable to most private construction projects, which
took effect on November 6, 2014. The
Retainage Law limits the ability of owners and contractors to negotiate
retainage, punchlist, and substantial-completion provisions of certain private
construction contracts. It applies to
any construction contract with an original contract price of not less than
$3,000,000, and to which the Massachusetts mechanic’s lien law, M.G.L. Ch. 254,
§§ 2 and 4, applies (i.e., contracts with prime contractors, all first- and second-tier subcontractors, and all
first- and second-tier suppliers). Residential construction projects consisting
of four or fewer units are exempt regardless of the contract value. All construction contracts executed after the effective date are subject to the new law.
The Retainage
Law limits the amount of retainage
withheld from each progress payment
to no more than five percent (5%) of the payment. The law also specifically defines “substantial
completion” as the stage of the project (or phase thereof, if applicable) at
which work “is sufficiently complete . . . so that the project
owner may occupy or utilize the work for its intended use.” Any contract terms which conflict with this
new statutory definition are void and unenforceable.
The Retainage Law also prescribes a timeline and
procedure for the release of retainage.
In general, retainage cannot be
withheld for more than 90 days after substantial completion and seven
additional days for each contract tier below the prime contractor. The Retainage Law imposes a new statutory form of notice of
substantial completion, which the prime contractor must submit to the owner
within 14 days after achieving “substantial completion.” The owner must accept or reject the substantial
completion notice within 14 days of receipt and must send the general
contractor a punchlist of deficient or incomplete items within 14 days after
the owner’s acceptance.
An owner may continue to withhold retainage,
in limited amounts specified by the Retainage Law, for incomplete or incorrect work or deliverables and for certain
outstanding claims. In such event, the
owner must, before the date payment is due, provide the party seeking payment
with written notice describing the deficient or missing work items and
deliverables, the basis of the outstanding claims, and the value attributable
to each.
The PowerPoint presentation in the link below provides
more detail on the timeline and process for releasing retainage and on other
aspects of the Retainage Law.
The text of the New Retainage Law can be found here.